施行地区 | 瑞穂町大字箱根ケ崎、大字長岡下師岡、大字石畑の各一部 | Readjustment districts: | A part of each Oaza Hakonegasaki, Oaza Nagaoka-shimomorooka, and Oaza Ishihata of Mizuho |
施行面積 | 176.7ha | Operational area: | 176.7ha |
施行期間 | 昭和49年8月1日~平成4年3月31日(換地処分) | Operation period: | August 1, 1974 - March 31, 1992 (replotting proceeded) |
業務委託 | 財団法人東京都新都市建設公社 | Subcontractor: | Tokyo New Cty Construction Public Corporation (Foundation) |
建設経費 Construction Expenditure | |||
金額 | Amount | ||
道路築造費 | Road construction cost | 3,741,520,000円 | 3,741,520,000 yen |
公園施設費 | Park facilities construction cost | 109,838,000円 | 109,838,000 yen |
排水施設費 | Drainage facilities construction cost | 279,100,000円 | 279,100,000 yen |
建物等移設費 | Relocation of building cost | 5,964,183,000円 | 5,964,183,000 yen |
水道等移設費 | Relocation of water supply cost | 58,037,000円 | 58,037,000 yen |
整地費 | Land leveling cost | 401,144,000円 | 401,144,000 yen |
調査設計費 | Survey and design fee | 3,133,638,000円 | 3,133,638,000 yen |
損失等補償費 | Compensation for losses | 433,015,000円 | 433,015,000 yen |
借入金利子 | Debt interest | 623,289,000円 | 623,289,000 yen |
事務費 | Office work | 401,328,000円 | 401,328,000 yen |
その他 | Other | 1,336,908,000円 | 1,336,908,000 yen |
合計 | Total | 16,482,000,000円 | 16,482,000,000 yen |
建設財源 Revenue for Construction | |||
金額 | Amount | ||
公共施設管理者負担金 | Public facilities administrator contribution | 1,786,064,000円 | 1,786,064,000 yen |
都交付金 | TMG grant | 2,945,362,000円 | 2,945,362,000 yen |
町負担金 | Town contribution | 2,152,491,000円 | 2,152,491,000 yen |
保留地処分金 | Reserved land disposal | 9,553,414,000円 | 9,553,414,000 yen |
その他 | Other | 44,669,000円 | 44,669,000 yen |
合計 | Total | 16,482,000,000円 | 16,482,000,000 yen |